Earthwork/Site Development
- Sample Projects |
|
|
Services | |
|
|
Evangeline
Downs Racetrack Sitework |
|
|
Jack County
Generation - Site Preparation |
|
|
Comite
Diversion at Lilly Bayou |
|
|
Site Development & Cooling Water Piping |
|
|
Site Development
|
|
|
Food Protein Recovery Plant |
|
|
|
|
|
Evangeline Downs Racetrack
Sitework |
|
|
|
|
|
|
|
Project: |
Evangeline Downs
Racetrack Sitwork |
|
Location: |
Opelousas, Louisiana |
|
Project Value: |
$4,414,000 |
|
Completion Date: |
December 2004 |
|
|
|
Project Description: |
|
|
|
James Construction Group served as
subcontractor, performing sitework in
preparation for expansion of the Evangeline
Downs Racetrack. The work involved the
following:
-
Clearing and stripping of 190 acres
-
432,000 CY of excavation/embankment
-
140,000 SY of soil cement
-
Laying 22,000 tons of asphalt
-
Installing 6 storm drainage structures
-
1,500 CY of concrete paving
-
6,500 LF of curb and gutter
-
Construction of sand track and turf track
|
|
|
|
|
Jack
County Generation - Site Preparation |
|
|
|
|
|
|
|
Project: |
Jack County
Generation
- Site Preparation |
|
Location: |
Jacksboro, Texas |
|
Project Value: |
$3,900,000 |
|
Completion Date: |
April 2004 |
|
|
|
Project Description: |
|
|
|
This project involved site preparation for a
combined cycle power plant. Construction
activities included the following:
-
Clearing of 40 acres
-
Excavation/embankment of 425,000 CY
-
Placement of 10,000 LF of storm drainage
-
Installation of a 5-acre liner in raw water pond
-
Construction of 2,500 LF access road
-
Laying of 15 acres of crushed stone
-
Placement of 70,000 CY of erosion matting
-
Installation of box culvert
-
Asphalt paving
-
Rip rap revelment
|
|
|
|
|
Comite Diversion at Lilly Bayou |
|
|
|
|
|
|
|
Project: |
Comite Diversion at
Lilly Bayou |
|
Location: |
Zachary, Louisiana |
|
Project Value: |
$2,423,312 |
|
Completion Date: |
October 2003 |
|
|
|
Project Description: |
|
|
|
This project was the first of four phases of the
Comite Diversion project. The project’s goal is
to reduce flooding of the Comite River in the
Amite River Basin. JCG was the prime contractor
on the project, and the scope of work included:\
-
Access road construction
-
Pipeline protection
-
Silt fence installation
-
Clearing and grubbing 120 acres
-
1,400,000 CY of excavation
-
86,700 vertical SF of slurry trench
-
Grassing and seeding
|
|
|
|
|
Site Development & Cooling Water Piping |
|
|
|
|
|
Project: |
Site
Development & Cooling Water Piping |
|
Location: |
Malvern,
Arkansas |
|
Project Value: |
$9,500,000 |
|
Completion Date: |
August 2001 |
|
|
Project Description: |
|
|
|
For this 500 MW power plant, JCG was awarded the
site development and the installation of the
cooling water process piping system for all
plant operations. Activities include:
-
Clearing and grubbing approximately 90 acres
-
75,000 cy of topsoil stripping
-
64 acres of soil stabilization
-
196,000 cy of excavation
-
172,800 cy of structural fill
-
63,000 tons of stone base material
-
Stormwater drainage, including 30 catch
basins, 4000 LF of concrete pipe culverts and
80 cy concrete drainage structure
-
600 LF 90” Price Bros. concrete pipe
-
4500 LF of access road
-
20 acres of seeding
-
60,000 sy of erosion control matting
|
|
|
|
|
Site Development
|
|
|
|
|
|
Project: |
Site Development
|
|
Location: |
Addis, Louisiana |
|
Project Value: |
$6,600,000 |
|
Completion Date: |
January 2000 |
|
|
Project Description: |
|
|
|
JCG was awarded the first construction package
for a new Polyvinyl Chlorite (PVC)
facility.
The scope of work in the site preparation
package involved 3 phases of construction: 1)
Earthwork 2) Underground pipe installation 3)
Concrete road paving.
Activities included clearing and grubbing,
topsoil stripping, construction of drainage
culverts and structures, installation of an
underground firewater system, and lime
stabilization. The scope of work also included
limestone surfacing and road base and the
construction of concrete roadways.
In total, the project required:
-
116,000 cubic yards topsoil stripping
-
250,000 cubic yards of excavation/fill
-
Installation of 10,200 linear feet of
underground firewater piping and 6,000 linear
feet of drainage pipe
-
120,000 tons of limestone placement
-
9000 cubic yards of concrete roadway
-
Rail spur installation
Due to the weather sensitivity of the sitework
scope, this phase of the project was extremely
critical to the overall project schedule. |
|
|
|
|
|
|
Food Protein Recovery Plant |
|
|
 |
|
|
|
Project: |
Food Protein Recovery Plant |
|
Location: |
Texarkana, Arkansas |
|
Project Value: |
$4,455,683 |
|
Completion Date: |
1998 |
|
|
|
Project Description: |
|
|
|
James Construction Group performed four separate
phases as a part of this total project. The
first phase was the construction of five miles
of the access road from US 67 north of Texarkana
to the site on the Red River. The second phase
was the site work and holding pond construction
for the plant itself. The third phase was the
site paving for the plant and the fourth phase
was the emergency construction of an additional
holding pond after start-up of the plant. The
project featured:
-
38 acres of clearing and grubbing for the sitework
-
Site and roadway excavation of 444,000 CYs
-
Installation of 31,600 CYs of clay liner for holding ponds
-
Lime stabilization for roadway of 110,000 SYs
-
Installation of 1,622 LF of HDPE drainage pipe
-
Concrete paving of 26,300 SYs
-
Emergency pond excavation of 46,000 CYs and pond liner of
13,700 CYs
-
Completed in 21 Calendar Days
|
|
|
|