|
|
|
|
JAMES
CONSTRUCTION GROUP |
|
| |
|
Environmental
- Sample Projects |
|
|
Services | |
|
|
Dewatering &
Dredging Operation |
|
|
Pond Drying |
|
|
Petro-Processor Site Remediation |
|
|
Coal Ash Pond
Upgrade |
|
|
|
|
|
|
Dewatering & Dredging Operation |
|
|
|
|
|
Project: |
Dewatering & Dredging Operation |
|
Location: |
Camden,
Arkansas |
|
Project Value: |
$193,150 |
|
Completion Date: |
August 2001 |
|
|
Project Description: |
|
|
|
JCG was awarded the contract to remove sludge
from an existing affluent sediment basin which
was to remain in operation during construction
activities. The following dredging activities
included:
|
|
|
|
|
Pond Drying |
|
|
|
|
|
Project: |
Pond Drying |
|
Location: |
Belle Chasse,
Louisiana |
|
Project Value: |
$3,700,000 |
|
Completion Date: |
May 2000 |
|
|
Project Description: |
|
|
|
JCG worked at this site for
four consecutive years, performing remedial
construction activities.
The alliance between JCG and the owner allowed the
owner/contractor project team to perform the
work in the most cost effective manner. While
onsite, JCG performed numerous remedial
construction activities which included pond
drying, landfill cell construction and landfill
closure, and other environmental related
projects.
The pond project required several earthwork
processing activities. The scope of work
included the dewatering and drying of
contaminated sludge material located in the
Pre-Equalization Pond, Oily Water Sludge Pond,
and the Equalization Pond. Construction
activities included:
JCG personnel were required to perform the work
in “fresh air” at all times. |
|
|
|
|
|
|
Petro-Processor Site Remediation |
|
|
|
|
|
Project: |
Petro-Processor Site Remediation |
|
Location: |
Baton Rouge,
Louisiana |
|
Project Value: |
$15,000,000 |
|
Completion Date: |
November 1996 |
|
|
Project Description: |
|
|
|
Remediation, construction and maintenance for
this “superfund” (hazardous waste) site has been
ongoing since 1987. T.L. James Industrial was
one of the prime contractors for over 10
years. JCG’s overall scope of work included
site preparation, haul roads, piling, bridges,
flood protection levees, hazardous waste
excavation, fugitive emission controls and
ground water recovery systems for the 45 acre
site. Key components of the project are listed
below:
-
35,000 linear feet of perforated HDPE piping in the bottom of
a contaminated cypress swamp
-
Trenching, sheet piling, installation of pipe, and the
backfill of the trench were all accomplished
while working under 4 to 6 feet of water to
minimize volatile emissions
-
Installation of 180,000 square feet of geogrid
and over 600,000 cubic yards of clay and sand
fill
-
Excavation and removal of contaminated sediments from over
2,700 linear feet of Baton Rouge Bayou
-
Installation of 350 ground water recovery wells
This project required the use of an extensive
health and safety plan, 29 CFR 1910.120
training, and the use of levels D, C, and B
personnel protective equipment. |
|
|
|
|
|
|
Coal Ash Pond
Upgrade |
|
|
|
|
|
Project: |
Coal Ash Pond Upgrade |
|
Location: |
Gulfport,
Mississippi |
|
Project Value: |
$4,200,000 |
|
Completion Date: |
November 1995 |
|
|
Project Description: |
|
|
|
The project site consisted of a 100 acre ash
pond with an existing 23 foot high containment
dike. The purpose of the pond is to collect ash
which is a by-product of coal combustion used to
generate electricity. Also, plant waste streams
are commingled in this pond. Geotechnical
studies revealed the operating water level of
the pond could not be increased without a
significant dike reinforcement. The scope of
work included:
-
Installation of geogrid reinforcing material along the
inside toe of the existing dike
-
Cut and fill operations of approximately 45,000 cubic
yards of clay and ash
-
Installation of 6900 LF of cement bentonite slurry
wall within the existing dike at approximately 55
vertical feet
-
Placement of 139,872 cubic yards of geogrid within
each compacted layer of fill material throughout the
length of the reconstructed dike |
|
|
|
|
|
|
|