Industrial - Sample Projects |
|
|
Services | |
|
|
Hydrogen
Plant Construction |
|
|
Northeast
Water Purification System |
|
|
Riverside
Heater Project |
|
|
Harrison County Energy Facility |
|
|
145 / 245
Expansion |
|
|
Carville
Energy Facility |
|
|
Coker Unit |
|
|
Air Separation & 80 MW Cogen Plant |
|
|
Mega Project |
|
|
|
|
|
Hydrogen Plant Construction |
|
|
|
|
|
Project: |
Hydrogen Plant
Construction |
|
Location: |
Westlake,
Louisiana |
|
Project Value: |
$10,400,000 |
|
Completion Date: |
July 2004 |
|
|
Project Description: |
|
|
|
James Construction Group, with its diverse
capabilities, performed several phases of work
on the Westlake hydrogen facility, including the
civil phase and the mechanical construction
activities on Phases I and II.
Civil Phase
-
Demolition and abandoned pipeline removal
-
Stripping, excavation, and embankment
-
Installation of 660 LF of 24˛ PVC pipe and 100
LF of 8˛ HDPE firewater piping
-
Placement of 5,000 tons 610 bahama stone
-
Erected formwork for 19 interconnecting
foundations
-
Installed rebar, anchor bolts and embeds
-
Placed 6,200 CY of concrete foundations
Mechanical Phase
-
Erection and assembly of reformer and
associated equipment
-
732 tons of refractory lined ductwork
-
284 tons of panels for radiant box
-
Key components to the reformer include radiant
section, convection section, steam drum,
process gas boiler area, PSA area, and
associated piping
-
1,858 tons of equipment to be set
-
Installation of nine large process module
skids
-
Installation and alignment of hydrogen
compressor skid and motor
-
Erection of 450 tons structural steel
-
Assembly and erection of elevated flare stack
and associated piping
-
Installation of water treatment system
-
Erection and assembly of the air cooler
support system and associated components which
include tube bundles, plenum, fans, motors,
motor mounts and belts
-
Installation of the oil/water separator system
-
Erection of the shell and tube heat exchanger
-
Assemble and install polyethylene tanks and
pumps
-
Install ammonia injection system skid
leveling, aligning skid, blower and motor
assembly
-
Erection of power distribution center and
analyzer buildings
-
Precommissioning
-
System testing and turnover
-
Installation of 28,000 LF of 1/2" to 30"
process pipe
-
Installation of 10,000 LF of radiant tubes
|
|
|
|
|
Northeast Water Purification
System |
|
|
|
|
|
Project: |
Northeast
Water Purification System |
|
Location: |
Humble, Texas |
|
Project Value: |
$5,300,000 |
|
Completion Date: |
January 2004 |
|
|
Project Description: |
|
|
|
Montgomery Watson Harza (MWH) subcontracted the
mechanical scope of work on this 40 mgd
water purification plant to JCG. JCG
performed piping, pump installation, and
equipment installation activities, including:
-
Installation of 6549 LF of carbon steel cement lined pipe ranging from
30˛
to 66˛
and 2,646 LF of carbon steel small bore pipe
ranging from 1/2˛ to 8˛
-
Installation of 328 LF of stainless steel small bore pipe and 815 LF of
stainless steel large bore pipe
-
Installation of 49,644 LF of PVC pipe
-
Installation of 2,828 LF of ductile iron pipe
-
Setting and installation of 121 pieces of
equipment, including pumps, mixers, tanks,
blowers and an air compressor
|
|
|
|
|
Riverside
Heater Project |
|
|
|
|
|
Project: |
Riverside
Heater Project |
|
Location: |
Geismar,
Louisiana |
|
Project Value: |
$1,056,000 |
|
Completion Date: |
December 2002 |
|
|
Project Description: |
|
|
|
JCG was awarded the contract on the design build
and replacement of the covection sections on
three existing gas fired heaters. The purpose of the project was
to improve overall performance and efficiency. JCG partnered with Born, Inc., who completed the
design, fabrication, and shipment of the
convection sections. JCG executed the schedule
to install the convection sections one unit at a
time to enable the Riverside facility to
maintain operations. The work was performed
under a turnaround situation and completed
within six days working twelve hour shifts per
unit. Construction activities included:
-
Building of heaters
-
Removal of existing stacks, Econ-o-mizers, and
platforms
-
Removal and replacement of three existing
convection sections
-
Addition of three 10 stacks
-
Testing of convection sections
-
Completion and turnover
|
|
|
|
Harrison County Energy Facility |
|
|
|
|
|
Project: |
Harrison
County Energy Facility |
|
Location: |
Marshall,
Texas |
|
Project Value: |
$14,000,000 |
|
Completion Date: |
November
2002 |
|
|
Project Description: |
|
|
|
The Harrison County Power Project is a 550MW
combined cycle power plant with 2 GE 7FA
turbines. JCGs scope of work included sitework,
concrete HRSG and Equipment foundations,
underground electrical and underground piping.
In total, JCG installed:
-
Site Preparation and Infrastructure
-
150,000 CY Excavation
-
14,000 CY Concrete HRSG and Equipment
Foundations
-
7000 LF Carbon Steel Piping
-
3000 LF HDPE Piping
-
1200 LF Price Bros. Piping
|
|
|
|
145 / 245
Expansion |
|
 |
|
|
|
Project: |
145 / 245
Expansion |
|
Location: |
Geismar,
Louisiana |
|
Project Value: |
$12,000,000 |
|
Completion Date: |
September 2002 |
|
|
Project Description: |
|
|
|
JCG was on-site throughout the expansion,
performing site preparation, concrete
foundations, steel erection, equipment setting,
piping, and final sitework and road paving.
Work was performed throughout the utility and
T-ox area, wastewater treatment plant, truck
loading area, and OSBL. In all, the scope
of work included:
-
Clearing, grubbing, and stripping a 15 acre site
-
3500 cy concrete road and ditch paving
-
500 tons of rebar
-
7500 cy concrete cooling tower, tank, pipe rack and
equipment foundations
-
400 tons structural steel erection
-
1500 LF HDPE, ductile iron and carbon steel piping
-
Equipment erection and alignment
|
|
|
|
|
Carville
Energy Facility |
|
 |
|
|
Project: |
Carville
Energy Facility |
|
Location: |
Carville,
Louisiana |
|
Project Value: |
$3,300,000 |
|
Completion Date: |
September 2001 |
|
|
Project Description: |
|
|
|
JCG installed the concrete foundations for this
550 MW Combined Cycle power plant, including the
foundations for the 2 GE 7FA Turbines. The
scope of work included fine grading, placing
concrete seal slab, forming foundations,
installing rebar and embeds, placing concrete
foundations, and wrecking the formwork. In
all, the project utilized:
-
666 tons of rebar
-
11,000 CYs concrete
|
|
|
|
|
Coker Unit |
|
|
|
|
|
Project: |
Coker Unit |
|
Location: |
Garyville,
Louisiana |
|
Project Value: |
$16,800,000 |
|
Completion Date: |
October 2000 |
|
|
Project Description: |
|
|
|
JCG constructed a 60 x 90 x 8 coke structure
base mat. This mat included 352 tons of
rebar with 25 tons of inbed structural steel.
The civil scope of work included:
-
14,000 CY concrete
-
(6) 70 High concrete columns
-
(1) Intermediate Deck
-
Concrete support beam 150 elevation w/12
deck elevated 50 high
-
Concrete table top elevated 70
-
Concrete walls and bridge crain
-
(1) Coke Pit
-
Miscellaneous steel erection
|
|
|
|
|
|
Air Separation & 80 MW Cogen Plant |
|
|
|
|
|
Project: |
Air Separation & 80 MW Cogen Plant |
|
Location: |
Geismar,
Louisiana |
|
Project Value: |
$25,500,000 |
|
Completion Date: |
January 2000 |
|
Manhours: |
464,546 |
|
|
Project Description: |
|
|
|
JCG received contract awards on the three major
phases of construction for the new Air
Separation plant: concrete/under- ground,
mechanical equipment/steel erection and process
piping. The grass root facility includes two
independent trains, each with the capability to
produce 1500 tons of oxygen per day. In
addition, JCG performed the civil construction
on the 80 MW Cogeneration Plant. JCGs scope of
work included:
-
Installation of approximately 10,490 CY of
concrete for heavy equipment foundations, cold
box foundations and elevated concrete
structures
-
11,490 LF of underground carbon steel pipe
-
Erection of 355 tons of structural steel
-
Cold box erection with alignment tolerances
within +/- 1/16 inch on a 5 piece 33 foot
diameter column at a total vertical height of
240 feet
-
16,558 LF stainless & carbon steel pipe in
cold boxes 1&2
-
60,000 LF of carbon and stainless steel piping
-
Compressor erection
-
Process equipment erection and alignment
The major equipment included: washer towers,
absorber vessels, refrigerant unit, water
chiller, heater skid, DeMag air compressors,
Atlas Copco nitrogen compressor, tanks, and the
filter box.
|
|
|
|
|
|
Mega Project |
|
 |
|
|
 |
|
|
Project: |
Mega Project |
|
Location: |
Garyville,
Louisiana |
|
Project Value: |
$18,000,000 |
|
Completion Date: |
September 1999 |
|
|
Project Description: |
|
|
|
The scope of work awarded to JCG on the
construction of the new polypropylene plant
consisted of the site development, all phases of
the civil construction, and structural steel
erection for a 45 acre grassroot site.
Activities included:
-
Grading, stripping, and excavation
-
Placement of approximately 150,000 CY of
backfill material, entrance and access roads
-
Installation of approximately 3,100 concrete
and timber piles ranging in lengths 60 - 95
LF in length and sheet piles
-
25,500 LF of underground carbon steel and HDPE
piping
-
12,000 CY of concrete foundations
-
Five spur rail entrance and fencing
-
Erection of approximately 1,500 tons
structural steel
-
Process equipment installation and alignment
|
|
|
|
|