HOME   |   EMPLOYEE LOG-IN   |  CONTACT US


Airport

Baton Rouge Metropolitan Airport
Runway 4L/22R Reconstruction - Phase I
Baton Rouge, LA

   
 

James Construction Group managed several different aspects of the reconstruction of Runway 4L/22R at the Baton Rouge airport. The acting runway was closed, and existing pavement removed. A cement-treated base was placed, and a 37.5 foot wide strip form pavement was installed. The project was completed with the reconstruction of the intersection of Runway 4L/22R and 13M/331R.

 

Project Scope:

 

·    49,100 SY of pavement removal

·    49,700 SY of cement treated base

·    49,100 SY of 15″ concrete paving

·    440 th asphalt paving

 

Project Value:  $4,200,000

 

11200 Industriplex Boulevard, Suite 150   Baton Rouge, Louisiana 70809   Phone 225.295.4830   Fax 225.295.4840

Site development by Keith A Horton, LLC