Industrial
S & B Engineers &
Constructors
Criterion Plant Expansion
Port Allen, LA
|
|
|
James Construction Group was
selected to perform the site
development, civil, and
mechanical phases of work on
a 40-acre expansion at
Criterion Catalyst and
Technology’s facility in
Port Allen.
Sitework:
·
Stripping of new plant area
·
Hauling of 97,000 CY of
structural fill
·
Placement of 1,050 tons of
lime for roadway
stabilization
·
Installation of the
following:
u 136,000 SY of
geotextile
u 57,000 tons of
610 limestone base
u 40 catch basins
u 720 LF of 96² corrugated metal pipe (CMP)
u 160 LF of 60² CMP
u 3,000 SY of
concrete paving
u 6,210 LF total
of HDPE drainage pipe
u 1,100 precast
piles
Civil Phase:
·
Excavation, backfill, and
rebar installation
·
Concrete foundations for
WPA structure, waste water
treatment, RIE unit, and
cooling tower
·
Excavation and
installation of 6,000 LF of
10-in. HDPE pipe
·
HDPE pipe testing
Mechanical Phase:
·
Erection of 600 tons of
structural steel
·
Equipment setting
·
Installation of elevated
concrete floor
·
Installation of...
u 3,600 LF of
stainless steel piping
u 1,300 LF of
lined carbon steel piping
u 15,000 LF of
fiberglass piping
u Testing of all
pipe systems
Project Value:
$31,577,000
|