Infrastructure
Ash Grove Cement Co.
Module B of New Landfill
Foreman, AR
|
|
|
James Construction Group was
the prime contractor on this
project to construct a
landfill for cement kiln
dust.
Project Scope:
·
42,000 CY of excavation
·
33,500 CY of embankment
·
36,000 tons of clay liner
·
400 LF of HDPE piping
·
500,000 SF of HDPE liner
·
32,000 CY of soil protective
cover
·
140 CY of concrete ditch
lining
·
2 acres of seeding
Project Value:
$1,315,000
|