Marine
Greater Ouachita Port
Commission
Greater Ouachita Port Dock
Facility
West Monroe, LA
|
|
|
In May 2006, the Greater
Ouachita Port Commission
awarded James Construction
Group a port expansion
contract that calls for the
construction of a dock
facility capable of handling
a 250-ton crane. The crane
will be used to offload
foreign and domestic
container cargo from barges
and transfer them to rail or
truck for distribution to
the Ark-La-Miss region and,
ultimately, to other
destinations throughout the
United States.
Project Scope:
·
Earthwork
·
Installation of sheet pile
wall
·
Driving 18″ concrete piles,
treated timber piles, and
steel pipe piles
·
Construction of two treated
timber mooring dolphins
·
Construction of a fender
system for the dock and
dolphins
·
Installation of concrete
deadmen and tie-back systems
to further stabilize the
sheet pile wall and dock
systems
Project Value:
$2,900,000
|